Seaton #1 Catholic School Construction Updates
Seaton #1 Catholic School Construction Updates
We are pleased to provide updates on the construction of the new Seaton #1 Catholic School on the webpage below. It is intended to keep students, families, staff, and the broader community informed through monthly updates, photos, and key project milestones.
Project Overview
Construction is underway for our brand-new Catholic elementary school at Hibiscus Drive and Burkholder Avenue in Pickering, scheduled to open in September 2027. This modern, state-of-the-art school will serve 622 students from Kindergarten to Grade 8 and will include a child care centre and an EarlyON Community Hub, creating a vibrant, faith-filled learning environment for the growing Seaton community.
The new school is being constructed to support the needs of the growing Seaton area of Pickering. This project represents a significant investment in Catholic education and will serve students for generations to come.
Key Facts:
- Opening: September 2027
- Location: 2460 Hibiscus Drive, Pickering
- Capacity: 622 students from Kindergarten to Grade 8
- Funding: The project is supported by $33.8 million in capital funding from the Government of Ontario, and we are grateful for their continued investment in Catholic education in Durham Region.
- Additional Features: Five-room child care centre (88 licensed spaces) and an EarlyON Community Hub
Project Milestones
Major milestones for the project include:
| Groundbreaking Ceremony |
Complete (November 2025) |
| School Naming |
Community consultation complete, and sent to the Ministry of Education for Approval |
| Foundation | In Progress |
| Structural Framing (Steel & Block walls) | In Progress |
| Exterior Envelop (Window, roof & cladding) | October 2026 – March 2027 |
| Interior Finishing | January - June 2027 |
| Site Works (Field, sidewalks, etc) | April - June 2027 |
| Substantial Completion | June 2027 (Opening for September 2027) |
Quarterly Construction Updates
Below are monthly updates highlighting construction activity, recent accomplishments, and what to expect next.
Start (November 2025) to March 2026 Update
Construction activities continued steadily from November 2025 to March 2026. Site preparation work progressed, including grading and underground servicing. Early foundation work began in designated areas, as well as some initial steel structural framing. Weather conditions have been challenging through the cold and snowy winter, with a wet spring, making for difficult conditions on the site.
Highlights:
- Completion of initial site grading;
- Installation of underground services;
- Foundations poured;
- Structural steel framing and masonry block walls started.
Photo Updates November 2025 - September 2027
Contact Information
For questions or feedback regarding the construction project, please contact: facilitiesservices@dcdsb.ca